How Much Concrete Do I Need?

How Much Concrete Do I Need?

One of the most common questions we hear from homeowners and contractors is:

“How much concrete do I actually need?”

Ordering too little can get expensive fast, unnecessary call-backs, wasted time, or worse, shutting a job down entirely. Ordering too much wastes money. And trying to guess usually ends with stress on pour day.

The good news is that concrete quantities are straightforward once you know how to calculate them.

Below is a simple, practical guide to help you figure out how much concrete you need for common projects without overthinking it.

The Basic Formula

Concrete is ordered by the cubic yard.

To calculate how much you need:

  • Measure the length (feet)

  • Measure the width (feet)

  • Measure the thickness or depth (inches)

Then use this formula:

(Length × Width × Thickness in inches) ÷ 300 = Cubic yards needed

Why 300?

The true conversion from cubic feet to cubic yards is 324. We use 300 intentionally to build in a small buffer. Concrete jobs rarely go exactly as planned, and being slightly heavy is far better than coming up short.

How Much Concrete Do I Need for a Driveway?

New concrete driveway in Statesville, NC

Let’s put this formula to use with a simple example.

Assume you’re pouring a concrete driveway.

A typical residential driveway might be:

  • 20 feet wide

  • 40 feet long

  • 4 inches thick

Calculation:

(20 × 40 × 4) ÷ 300 = 10.67 cubic yards

In real life, you’d order 10.75–11 yards.

Pro tip

Be very sure of your depth measurement. If that driveway averages 4.5 inches instead of 4, the total jumps to 12 yards. At 5 inches, it climbs to 13+ yards.

In our experience, guessing at depth or having an uneven base with deeper spots is the most common reason jobs run short.

Always round up, not down. Most batch plants have a minimum of 1 yard. If you end up 0.25 yard short, you’ll still need to order a full yard to finish the job.

How Much Concrete Do I Need for a Slab?

For slabs like sheds, workshops, or additions, thickness matters.

Barndominium slab in Mooresville, NC

Example slab:

  • 40 feet × 40 feet

  • 4 inches thick

Calculation:

(40 × 40 × 4) ÷ 300 = 21.33 yards

You’d order 21.5 yards.

If the slab is thicker (6 inches), rerun the math — thickness adds up fast.

Pro tip

Our trucks typically carry 10 yards at a time. When a job is close to a number divisible by 10 (like 21 yards), you can order “20+”.

That means we’ll deliver 20 yards first. Once that concrete is down, you can take a measurement and call in the balance needed to finish. This often saves you from over- or under-ordering on the final truck.

How Much Concrete Do I Need for Footings?

Footings are usually long, narrow, and deeper than slabs.

Example footing:

  • 40 feet long

  • 2 feet wide

  • 12 inches deep

Calculation:

(40 × 2 × 12) ÷ 300 = 3.2 cubic yards

You’d order 3.25 yards.

Bagged Concrete vs Ready-Mix

A common mistake is underestimating how much labor and expense bagged concrete really involves.

We’ve written about this before.

As a rough comparison:

  • 1 cubic yard = 45–50 80-lb bags

So a 2-yard project means:

  • About 100 bags

As of January 2026, Lowe’s lists 80-lb bags at $5.98 each:

100 × $5.98 = $598 (before tax)

That doesn’t include:

  • Delivery or store trips

  • Loading and unloading

  • Mixing by hand in a wheelbarrow (hours of hard labor)

  • Or renting a mixer

By comparison, if we deliver 2 yards, the typical cost is about $726 before tax. That $128 difference is more than worth the time, effort, and physical toll of handling 100 bags. And that doesn’t even factor in mix quality or consistency.

That’s why many homeowners and contractors switch to ready-mix delivery once a project goes over 1 yard.

Common Mistakes to Avoid

  • Guessing instead of measuring. Don’t eyeball it, use a tape measure!

  • Forgetting thicker edges or turned-down slabs

  • Not accounting for grade variations

  • Ordering exactly the calculated amount with no buffer

Concrete is unforgiving. Being short by even half a yard can create real problems.

FAQ’s

Do I need to add extra concrete to my order?

Yes. We always recommend ordering a small buffer. Concrete jobs rarely go perfectly, and being short is far more expensive than having a little extra. Uneven subgrades, thicker edges, or slight measurement errors can add up quickly. That’s why we use a conservative calculation and encourage rounding up.

What happens if I come up short on a pour?

If you run short, you’ll need to order additional concrete, and most batch plants have a minimum of one yard. That means even being a quarter-yard short can turn into an extra truck and added cost. Planning ahead and ordering enough the first time helps avoid delays and unnecessary expense.

Can I order concrete if I’m not a contractor?

Yes. Homeowners regularly order concrete for driveways, slabs, footings, and small projects. If you’re unsure about measurements or what makes sense for your job, we’re happy to help walk through it with you before scheduling delivery.

Need Help Figuring It Out?

There are plenty of solid concrete calculators available online, including this concrete volume calculator. Just keep in mind that most calculators don’t include a buffer and assume perfect conditions, which leaves little margin for error on real-world pours.

If you’re unsure about measurements, thickness, or whether ready-mix makes sense for your project, we’re happy to help.

A quick phone call can save you:

  • Time

  • Money

  • A stressful pour day

Contact Rocket Concrete or request a quote, and we’ll help you make sure you order the right amount the first time.

Rocket Concrete provides dependable concrete delivery with clear communication, specializing in small and short loads for homeowners and contractors across North Carolina.